Key dates
Improvements to the area will begin in September and run until March 2016. The work will be completed in stages to keep disruption in the area to a minimum.
Start date | Work programmed |
---|---|
September 2015 | - Preparation works to make way for the new improvements - Begin work to reinstate the carriageways on selected roads. |
October 2015 | - Begin public space improvement works - Begin work on 'Copenhagne' crossings. |
November/ December 2015 | - Continue work on public space improvements. |
January/ February/ March 2016 | - Implement road closures - Public space improvements completed. |